EDP has chosen Elevolution Engenharia to execute several projects at the Baixo Sabor Hydroelectric Power Station in Torre de Moncorvo.

The project has four fronts involving different works next to the Upstream Dam of the Baixo Sabor Hydroelectric Power Station: construction of the observation and control centre and diesel group, access to the observation and control centre, architectural work at the portal to the power plant access gallery and final landscaping of the right bank.

The main works include block retaining walls, construction of several reinforced concrete structures, architectural finishes, hydraulic and electromechanical infrastructure inside the observation and control centre, drainage and paving work for landscaping.

The works are due to last for 6 months and start this month.