Tecnasol Angola secures slope stabilization at the Laúca Dam

2014-12-14
This is a slope 71.489 m2 (500 m long by 143 m high), where the following activities are planned:

- 2 Lifelines 500 m long and 5,000 m of nailings
- 500 m Dynamic Barrier 3 m high
- 71.489 m2 of deforestation and removal of blocks
- 71.489 m2 of application of netting
- Carrying out 91.659 m of nailing
- Application of 1.764 m3 of reinforced concrete